Project details
Locations: Ashburton, Balwyn, Camberwell, Greythorn & Hawthorn
Timing: March - May 2024
Budget: Under $500k
Project overview
This project consisted of 5 Boroondara library refurbishments. Reconfiguring the book return chute, to accommodate new book sorter configurations.

Process
Foursite completed 5 separate projects for the city of Boorondara, each at separate locations. These projects were all completed in a live environment, meaning children and adults from the public needed to be protected at all times. We delivered this project ahead of time and were praised for our delivery method. Our tender submission was highly questioned due to our ambitious delivery timeframe; however, we were praised once it was achieved.
Outcome
This short program meant that not only were the works completed quickly, but the budget was highly competitive due to our reductions in overheads.